Construction of a new facility is planned and it is known that the facility will be subject to part 70 (Title V). When does the Title V application need to be submitted?
A Title V application nees to be submitted to the Air Protection Branch within one year of beginning operation as a major source. An SIP Construction & Operating permit application should be submitted as soon as possible as processing time varies depending on facility location, size and quantity of air pollutants.