Can I pour a concrete slab in the building after the construction is completed?
Yes. National Barn Company uses a 2 x 6 CCA treated bottom plate around the bottom of the building. This board can be used as a form for pouring a concrete slab. Concrete can normally be poured through the large door opening. If the concrete contractor requires additional access to pour the concrete then some wall metal could be left off and installed by the customer after the concrete is poured. In some instances, National Barn Company can set the posts for the building and pull off the job until the concrete is complete. This may require additional cost for travel expenses for the crew.