Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Can a Notice to Proceed (NTP) with construction be issued with outstanding PD-02 Exception Letter issue(s)?

0
Posted

Can a Notice to Proceed (NTP) with construction be issued with outstanding PD-02 Exception Letter issue(s)?

0

A2. PD-02 exception letters routinely request authorization to proceed to bid advertisement and bid opening given some incomplete PD-02 required items. This request must list the outstanding items and include a resolution plan for each of them. Most often PD-02 exception letters only request permission to proceed with advertisement and are silent regarding the question of proceeding with contract award. In the latter cases, the Office of Pre-Letting QA staff has been tasked to follow the outstanding PD-02 issues by periodically querying the PL/CPM/LAL regarding the status of the resolution plan. When the PL/CPM/LAL has confirmed that all the listed issues have been resolved, the ODOT Procurement Office Construction Contracting Unit can be so advised and will then proceed with contract award. This notification needs to be in writing (e-mail preferred) and can be directed to the project QA engineer, to OPO Construction Contracting directly, or both. Unless PD-02 letters explicitly reques

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123