At what point in the 60 days should the EAs preliminary determination on a modified or revised permit application go to CIWMB staff for comment?
Answer 2: Section 21660.3(b) requires the EA to notice the CIWMB of its preliminary determination on a modified or revised permit application after finding the permit application complete and correct and within 60 days of receipt of the application by the EA. In addition, for revised permits, the notice should be sent to CIWMB staff at least 10 days prior to the date of the informational meeting to allow sufficient time for the CIWMB staff to provide comments, if it decides to do so.
Related Questions
- If CIWMB staff disagree with the EAs preliminary determination for a modified or revised permit application, who has final authority to make the determination?
- At what point in the 60 days should the EAs preliminary determination on a modified or revised permit application go to CIWMB staff for comment?
- What influence do comments by CalRecycle staff have on the EAs preliminary determination for a modified or revised permit application?