Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Are there estimated dates (e.g., grant award, grant agreement execution) we must use in making our program schedule in accordance with IV(B)(1)(b)(i)(C)?

0
Posted

Are there estimated dates (e.g., grant award, grant agreement execution) we must use in making our program schedule in accordance with IV(B)(1)(b)(i)(C)?

0

No, you are not required to use specific dates for purposes of the schedule required for the threshold at Section IV(B)(1)(b)(i)(C). Rather, it is essential that applicants ensure their program schedule follows the revitalization grant implementation requirements of Section XVI(C). Applicants should clearly indicate on their program schedule the estimated dates they are using. However, HUD suggests the use of the following dates for the sake of consistency.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123