Are raised floors installed before or after MEP works?
There are two schedules that can be followed. ALTAIR raised floor can be installed before any other trades enter a job-site (provided that the floor is protected during the continuation of works at site). The other alternative is to install RFT floors after all MEP (Mechanical / Electrical / Plumbing) works are done, provided that such works have been executed following a 600mm x 600mm grid previously approved by ALTAIR.
Related Questions
- Electronics are commonly installed in rooms with raised floors. What issues need to be addressed when installing precision air conditioning in this type of facility?
- What are the advantages and disadvantages of different carpet tile systems that are commonly installed on raised floors?
- Where are raised floors typically installed?