Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Are pre-notices for a Colorado Mechanics Lien Claim required?

0
Posted

Are pre-notices for a Colorado Mechanics Lien Claim required?

0

Yes. At least 10 days prior to filing a Colorado mechanics lien statement, the claimant must provide a notice of intent to the owner and the prime contractor.