Any suggestions on using Summit Micros hot swap controllers?
It is important when defining a system’s sequencing requirement that SynQor’s 200ms initialization period be considered. As an example, if you are using a programmable delay to enable multiple converters in a specific sequence, you must make sure the delay is approximately 200ms. When using the Summit Micro devices, make sure to use their 160ms delay setting, and use the second delay tap to enable the first converter. As an example for a three converter solution you use the SMH4804 where PG#2 would enable the first converter, PG#3 for the second and so on.