Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Along that same line as question #8 above, how does TrakPro handle the estimate-to-complete (ETC) cost projection?

COST line projection trakpro
0
Posted

Along that same line as question #8 above, how does TrakPro handle the estimate-to-complete (ETC) cost projection?

0

Peter Buitenhek Answer: A tertiary line is added when Estimate-to-Complete (ETC) costs are forecast for project completion. If the ETC line falls below the contract line, the final costs will be below contract goals (yea). Conversely, a line above the contract will signify costs above the goal and suggests cost-saving or limiting measures should be implemented by management.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123