Along that same line as question #8 above, how does TrakPro handle the estimate-to-complete (ETC) cost projection?
Peter Buitenhek Answer: A tertiary line is added when Estimate-to-Complete (ETC) costs are forecast for project completion. If the ETC line falls below the contract line, the final costs will be below contract goals (yea). Conversely, a line above the contract will signify costs above the goal and suggests cost-saving or limiting measures should be implemented by management.