Since I have sent quarterly MC Checklists throughout the project’s construction, do I still need to complete and send another checklist with all pay items filled out and signed for the final?
When the first quarter is submitted, it is advisable to make a copy (after it has been signed) that can be added to for the next quarter. When the second quarter checklist is ready for submission, make a copy of it (after it has been signed) which will now include all material requirements and signatures for two quarters. Continue this procedure of making copies of materials already used and signed for each quarter, and at the end of the project, you will have a Final MC Checklist completely filled out. This method will eliminate finding missed pay items at the end of the project. A blank copy of the checklist is not needed for each quarter.
Related Questions
- Since I have sent quarterly MC Checklists throughout the project’s construction, do I still need to complete and send another checklist with all pay items filled out and signed for the final?
- Do I pay First General Services and ServiceMaster 380 when the project is complete, or will I make periodic payments at various stages of the construction process?
- If I complete the design work for a project, can I be selected to perform construction management or construction inspection services for the contract?